projects  
   
NO CONTRACT NAME START/END  
91.

CIMPOR YIBITAŞ Hasanoğlan Cement Factory, Cement Silo and Handling System, Manufacturing, Construction, Installation Works, 5500 m3. ANKARA

2007/2008  
90.

İSDEMİR, PCI Landscaping, Construction of Blast Furnace Stove Gas Line, Fire Protection Water Tank and Pump Building Works. İSKENDERUN  

2007/2008  
89.

İSDEMİR, Blast Furnace No:4 Raw Material Handling Lines, Engineering, Manufacturing, Construction, Installation Works. İSKENDERUN 

2007/2008
88.

İSDEMİR, Steam Boilers, Steel Structure Works.
İSKENDERUN

2006/2007  
87.

İSDEMİR, No:1 and 2 Slab Reheating Furnace Construction and Erection Works, 2 x 400 t/h. İSKENDERUN

2006/2008
86.

İSDEMİR, 1600 m3 Demineralized Water Tank, Manufacturing and Installation Work. İSKENDERUN 

2006/2006  
85.

İSDEMİR, No:6 and 7 Steam Boilers, Construction of Reinforced Concrete  Stack, 110m. İSKENDERUN

2006/2007  
84.

İSDEMİR, Blast Furnaces Pulverized Coal Injection Facility, Construction, Manufacturing, Installation Works, 1.000.000 t/y.  İSKENDERUN

2005/2006
83.

İSDEMİR, Construction of No: 3 Blast Furnace Steel Stack, 65 m.
İSKENDERUN

2006/2006  
82.

ERDEMİR, No:4 Slab Reheating Furnace Civil Works and Process Installation, 220 t/h. Kdz. Ereğli - ZONGULDAK 

2004 / 2005
81.

EÜAŞ, Tunçbilek Power Plant, Rehabilitation of 5. Unit Concrete Stack. KÜTAHYA 

2003 / 2004  
80.

ENERJİSA, Installation Works of 42 MW GT 6000 BEV Gas Turbine and Auxiliary Facilities. ÇANAKKALE

2002 / 2002
79.

Transfer of Operational Rights (TOR) of coal fired Yatağan (630 MW) Kemerköy (630 MW) and Yeniköy (420 MW) power plants from TEAS by INTERNATIONAL POWER PLC (UK), VAKIF ENERGY Inc., ANKARA ENERGY AND PRODUCTION Inc. and MİMAG Inc.  Consortium. MUĞLA (Delivered back to TEAŞ)

1997 / 2006  
78.

Realisation of 770 MW Ankara Natural Gas Fired CCGT Project on BOO (Built-Own-Operate) basis by SUEZ ENERGY INTERNATIONAL - SEI (PRIMEROFIN B.V., TELFIN S.A., COMPAGNIE EUROPEENNE DE DEFINANCEMENT S.A, BELGELECTRIC FINACE B.V.) and  MİMAG Inc. Consortium. ANKARA  

1998 / 2018
77.

TMO (Turkish Grain Authority), Harbour Silo at Derince. Rehabilitation
of Earthquake Damages and Measures for the Protection against
Earthquakes. Derince - İZMİT

2001 / 2002
76.

BAYMİNA ENERGY S.A., Maliköy Preliminary School Construction Works, Polatlı - ANKARA   

2002 / 2002  
75.

EÜAŞ, Ambarlı Power Plant, 4. and 5. Group Stacks Construction.
İSTANBUL 

2000 / 2000  
74.

STANDARD FASEL-LENTJES (MODERN ENERGY) Heat Recovery Steam Generator (HRSG), Installation Work, 66t/h. Kırkgöz - ÇORLU 

2000 / 2000
73.

UNIMAR, 480 MW Combined Cycle Gas Turbine (CCGT), Complete Periodical Maintenance Works. MARMARA EREĞLİSİ    

2000 / 2000  
72.

ZORLU ENERGY 42 MW Combined Cycle Gas Turbine (CCGT), High Pressure Steam Distribution Pipes, Erection, Testing And Commissioning Works. LÜLEBURGAZ. 

2000 / 2000  
71.

DIRECTORATE OF NATIONAL EDUCATION, HASANKADI Preliminary School Construction Works. BARTIN 

2000 / 2000  
70.

TMO, 60 tons capacity Electronic Weighbridges Stations for Loading and Unloading (5 units) 

1999 / 2000  
69.

ZORLU ENERGY; Bursa Power Station, 35 MW Second Combined Cycle System Steam Turbine, Condenser and Piping Installations, Tests and Commissioning Works. BURSA 

1999 / 2000  
68.

ZORLU ENERGY; Combined Cycle Power Plant, Naphta Tanks.
LULEBURGAZ 

1999 / 2000  
67.

TEKSER (BOSEN); Waste Heat Boiler, 100t/h Steam Turbine Generator, Condenser and Auxiliary Machinery & Equipment. Complete Installation, Testing and Commissioning Works. BURSA 

1999 / 1999
66.

TMO - Repairing and Commissioning Work of Seaport-Silos.
İZMİT 

1999 / 1999  
65.

ZORLU ENERGY; "42 MW, LM6000 gas-turbine-generator" installation, testing and commissioning works, LÜLEBURGAZ 

1999 / 1999  
64.

BIS ENERGY, "45 MW Steam Turbine" Installation, Testing and Commissioning Works. BURSA

1998 / 1999  
63.

ZORLU ENERGY,"42 MW, LM6000 Gas-Turbine-Generator" Installation, Testing And Commissioning Works. BURSA 

1998 / 1999  
62.

GSD. (BIS ENERGY), Waste Heat Recovery Generator's Piping And Instrument Installation Works. BURSA 

1998 / 1998  
61.

ZORLU ENERGY; Manufacturing and Installation of Naphta Tank for Combined Cycle  Power Plant. BURSA 

1998 / 1999  
60.

TEKSER (BOSEN), "50 MW Westinghouse Gas-Turbine-Generator" Installation, Testing And Commissioning Works. BURSA

1998 / 1998  
59.

NOOTER/ERIKSEN (BIS ENERGY), Waste Heat Recovery System Erection With Stack Manufacturing And Erection Works, with a capacity of 87 t/h steam and 47 t/h Hot Water. BURSA 

1998 / 1999
58.

MITSUI&CO-TURK TRACTOR FACTORY, Security System Installation Works. ANKARA 

1998 / 1998  
57.

BIS ENERGY, "42 MW, LM6000 Gas-Turbine-Generator" Installation, Testing And Commissioning Works. BURSA 

1998 / 1998  
56.

BISAŞ, High Pressure Steam Piping Between BİSAŞ And Bis Energy Gas Fired Combined Cycle Power Plant. BURSA 

1998 / 1998  
55.

ZORLU ENERGY, "35 MW, LM2500 Gas-Turbine-Generator And Steam-Turbine-Generator" Installation, Testing And Commissioning Works. BURSA

1998 / 1998
54.

UNI-MAR, "480 MW 2 units of Gas-Turbine-Generator and 1 unit of Steam-Turbine-Generator" Installation, Testing and Commissioning Works. MARMARA EREĞLİSİ 

1997 / 1998
53.

BIS ENERGY, "38 MW, G.E.60001B/Frame 6 type Gas-Turbine-Generator" Installation, Testing And Commissioning Works. BURSA 

1997 / 1997
52.

TMO, 7 units of Truck Lifting Platforms, Design, Supply, Installation and Commissioning Works.

1996 / 1998  
51.

BUSKI Rehabilitation of Demirtaş Solid Waste Dumping Site.
BURSA  

1994 / 1996  
50.

ÇAMSAN, Medium Density Fibreboard Factory, Main and Anvillary Buildings Construction Equipment Supply and Installation. ORDU   

1994 / 1995  
49.

BISAŞ, "50 MW Combined Cycle Power Plant LM5000 Steam Injected Gas-Turbine And Generator" Installation, Testing and Commissioning Works. BURSA 

1993 / 1993
48.

TMO, 39 no.s 60 tons Weighbridge Stations for Loading and Unloading Stations at 39 Sites. 

1992 / 1993  
47.

105 MW Gas Power Plant Dismantling, Transportation and Installation. SEYDİŞEHIR / NAHCIVAN 

1992 / 1993
46.

AZERBAIJAN ELECTRICITY AUTHORITY; 154 kV, Transmission Line, 90 km. IĞDIR - TURKEY / NAHCEVAN - AZERBAIJAN.

1992 / 1992  
45.

Construction of 2 Reinforced Concrete Cement Silos. Hasanoğlan
ANKARA 

1991 / 1991  
44.

Manufacturing and Erection R/L Towers for PTT Administration (7 locations)

1991 / 1991  
43.

TCDD, İskenderun-Divriği Railway Electrification Project, Supply of Catenary Hardware and Installations.

1990 / 1990  
42.

380 kV Transformer Substations (MİMAG-BOYTAŞ). SİNCAN, GAZİANTEP, DİYARBAKIR

1989 / 1992
41.

Turkish State Railways Sincan-Eskisehir Railway Electrification,
280 km. (IRCON-INDIA / MİMAG)

1989 / 1991
40.

PTT Members Cooperative, 400 unit of Dwelling House Construction and Heating Centre. ANKARA

1987 / 1987  
39.

WEST ANATOLIA Cement Factory, construction 2 no.s Post Tensioned Reinforced Concerete Cement Silo. İZMİR 

1987 / 1987  
38.

TMO, 210 000 tonnes Capacity Steel Silos and Ancillary Buildings, (Attila Doğan Construction and Installation Co., Phenix Rousies S.A., MIMAG Construction and Trade Inc.) 

1987 / 1989  
37.

Ankara Metropolitan Municipality, Kıbrıs Village Bitumen Tanks, Hot Oil and Heating Facilities  Installations. ANKARA    

1987 / 1987  
36.

ETİBANK, Mazıdağı Social Facilities Heating Centre and 2 Stack Construction. MARDİN 

1986 / 1986  
35.

Esenboğa Airport Control Tower Construction.
ANKARA   

1985 / 1985  
34.

TEK, Afşin Social Facilities Heating Centre Stack Construction.
AFŞİN   

1985 / 1985  
33.

GÖHAS, Atatürk Lung Dieases Centre Rehabilitation Construction.
ANKARA   

1985 / 1985  
32.

Karabük Iron and Steel Works, 2. Coke Battery Stack and Gas Channels Construction. KARABÜK

1985 / 1985  
31.

TUSAŞ, Medium Voltage Substation Building Construction. Mürted
ANKARA   

1985 / 1985  
30.

MKEK, Çankırı Military Weapons Factory, Heating Centre Construction.
ÇANKIRI

1984 /1984  
29.

Efes Pilsen Anatolia Malt and Brewery Factory, 5000m3 Water Tank, Waste Water and Infrastructure Construction. ÇUMRA 

1983 / 1985  
28.

TEK, Kangal Thermal Power Plant, 2 no.s Reinforced Concrete Stacks Construction, 120m. Kangal - SİVAS 

1983 / 1985
27.

Slipforming Consultancy, Karakaya Railroad Bridge Construction. 

1982 / 1982  
26.

TRT, Elbistan TV Transmitting Station and Ancillary Buildings Construction. ELBİSTAN 

1982 / 1986  
25.

Efes Pilsen Anatolia Malt and Brewery Factory, 30 000 tonnes Silo, Machine House, Loading and Unloading Facilities Construction. ÇUMRA 

1982 / 1984
24.

Aziz Yağcı Flour Factory, Silo Construction,10.000 t.
UZUNKÖPRÜ 

1982 / 1982  
23.

Ministry of Defence, GATA Heating Centre Construction.
ANKARA 

1981 / 1982  
22.

TEK, Çayırhan Thermal Power Plant, 2 no.s Reinforced  Stack Construction,120m. Çayırhan - ANKARA 

1981 / 1982  
21.

National Intellegence Agency, Heating Centre Construction.
ANKARA 

1981 / 1982  
20.

Ereğli Iron and Steel Works, Dressing and Washing Building.
EREĞLİ 

1980 / 1981  
19.

Thrace Oil Seed Agriculture and Trade Cooperative Association, Çorlu Grain Silo Construction 8.000 t. ÇORLU 

1980 / 1981
18.

Dwelling House Construction. Gaziosmanpaşa
ANKARA

1980 / 1983  
17.

EGE Malt and Brewery Co., Akköy Reinforced Concrete Barley Silo Construction10,000 t. KONYA 

1979 /1980  
16.

EGE Malt and Brewery Co., Silo and Mill Pile Foundation Construction.
İZMİR

1978 / 1978  
15.

EGE Malt and Brewery Co., Acıkuyu Reinforced Concrete Barley Silo Construction,10.000 t. KONYA 

1979 / 1980  
14.

EGE Malt and Brewery Co. İzmir Beer Factory, Reinforced Concrete Silo Construction, 5.000 t. İZMİR

1978 / 1978  
13.

EGE Malt and Brewery Co., Afyon Malt Factory Dosage Silo Construction, 3.000t. AFYON 

1978 / 1978  
12.

Turkish Pulp and Paper Industries, Akdeniz Paper Mill Water Supply Facilities Construction. SİLİFKE

1978 / 1981  
11.

Ankara Golf Club Security Facilites Construction.
ANKARA 

1978 / 1978  
10.

TCDD, Sivas Concrete Sleeper Factory, Aggregate Silos and Pile Foundation Construction. SİVAS   

1978 / 1978  
09.

PETLAS, Tire Factory Security Facilities Construction.
KIRŞEHİR 

1978 / 1978  
08.

MKEK, Polatlı Construction Machines Factory, Security Facilities Construction. POLATLI

1978 / 1978  
07.

MKEK, Çankırı Military Weapons Factory, Security Facilities Construction. ÇANKIRI 

1977 / 1978  
06.

State Airports Administration, Airport Control Tower Construction.
ADANA 

1977 / 1977  
05.

State Airports Administration, Airport Control Tower Construction.
TRABZON 

1976 / 1976  
04.

State Airports Administration, Airport Control Tower Construction.
ANTALYA 

1976 / 1976  
03.

Ministry of Culture and Tourism, Museum Construction.
ÇANKIRI 

1976 / 1976  
02.

Office Building Construction.
HACIBEKTAŞ

1975 / 1975  
01.

Ministry of Culture and Tourism, Museum Construction.
HACIBEKTAŞ

1975 / 1976  
 

 
 

home | company profile | field of activities | projects | mimag-samko | baymina energy | contact

izci sok. no: 18 g.o.p ankara tel: 312.436 3036 faks: 312 437 2853 e-posta: info@mimag.com.tr